Title
Authorize the City Manager to finalize and execute a Professional Engineering Services Contract with Halff Associates, Inc., for the Mesquite Erosion Mitigation in the amount of $692,000.00.
Body
This project will provide erosion mitigation solutions to protect existing infrastructure from future erosion at four sites located along South Mesquite Creek and Stream 2B4 within the City of Mesquite:
• Site 1A: Stream 2B4 adjacent to SecurCare Self Storage
• Site 1B: Stream 2B4 adjacent to SMS Clinical Research
• Site 2: South Mesquite Creek at the drainage flume behind Chamberlain Place
• Site 3: South Mesquite Creek adjacent to Bruton Park
Financial Implications
Funding for this project has been allocated with Drainage Utility District (DUD) Funds.
Recommended/Desired Action
Staff recommends the City Manager be authorized to finalize and execute a Professional Engineering Services Contract with Halff Associates, Inc.
Attachment(s)
Location Maps
Drafter
Tracy Romo
Head of Department
Eric J. Gallt, P.E.