Legislation Details

File #: 26-8493    Version: 1 Name: Change Order No. 1 to Bid No. 2025-059 - Trinity Pointe Elevated Storage Tank
Type: Agenda Item Status: Consent
File created: 11/4/2026 In control: City Council
On agenda: 11/16/2026 Final action:
Title: Authorize the City Manager to finalize and execute Change Order No. 1 to Bid No. 2025-059, Trinity Pointe Elevated Storage Tank, with Landmark Structures I, L.P., in the amount of $86,471.00. ?
Attachments: 1. Change Order No. 1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Authorize the City Manager to finalize and execute Change Order No. 1 to Bid No. 2025-059, Trinity Pointe Elevated Storage Tank, with Landmark Structures I, L.P., in the amount of $86,471.00.

​

Body

Bid No. 2025-059 was approved by City Council on April 24, 2025, in the amount of $8,160,200.00. This change order provides for installation of an additional 24-inch sewer line not completed by the Fire Station contractor, Crossland Construction Company, Inc., and extension of the ornamental fencing along the west side of the property, including columns, 8-foot piers, and a mowing strip.

 

Change Order No. 1 increases the contract by $86,471.00, bringing the revised contract amount to $8,246,671.00, and adds 69 calendar days to the contract.

 

Financial Implications

Funding is available through bond funds in Project B0057.

​

Recommended/Desired Action

Staff recommends the City Manager be authorized to finalize and execute Change Order No. 1.

​

Attachment(s)

Change Order No. 1

​

Drafter

Tracy Romo

​

Head of Department

Eric J. Gallt, P.E.