Title
Authorize the City Manager to finalize and execute Change Order No. 1 to Bid No. 2025-059, Trinity Pointe Elevated Storage Tank, with Landmark Structures I, L.P., in the amount of $86,471.00.
Body
Bid No. 2025-059 was approved by City Council on April 24, 2025, in the amount of $8,160,200.00. This change order provides for installation of an additional 24-inch sewer line not completed by the Fire Station contractor, Crossland Construction Company, Inc., and extension of the ornamental fencing along the west side of the property, including columns, 8-foot piers, and a mowing strip.
Change Order No. 1 increases the contract by $86,471.00, bringing the revised contract amount to $8,246,671.00, and adds 69 calendar days to the contract.
Financial Implications
Funding is available through bond funds in Project B0057.
Recommended/Desired Action
Staff recommends the City Manager be authorized to finalize and execute Change Order No. 1.
Attachment(s)
Change Order No. 1
Drafter
Tracy Romo
Head of Department
Eric J. Gallt, P.E.