Bid No. 2026-053 - Paving and Utility Improvements for Edgemont Park.
(Authorize the City Manager to finalize and execute a contract with Estrada Concrete Company, LLC, in the amount of $10,326,039.00.)
Body
Name of Department
Public Works - Engineering
Project/Budgeted Amount
$10,327,000.00
Sum of Bid/Bid Amount
$10,326,039.00
This project will reconstruct residential concrete streets, sidewalks, and driveways. It will also include utility upgrades with over 1,000 linear feet of 8-inch water line and 11,000 linear feet of 8-, 10-, and 12-inch sanitary sewer lines.
This project is anticipated to begin June 1, 2026, and to be completed by June 1, 2027.
Bid notices were broadcast through BidNet Direct electronic procurement system, posted on the City’s website, and published in the Daily Commercial Record newspaper. A total of four responsive bids were received. A low responsive bid of $10,326,039.00 was submitted by Estrada Concrete Company, LLC.
Financial Implications
The allocated funding is from the Real.Texas.Roads. Street Bond and Water and Sewer funds.
Recommended/Desired Action
Staff recommends that the City Manager be authorized to finalize and execute a contract with Estrada Concrete Company, LLC.