RFP No. 2026-105 - Paving and Utility Improvements for Brazoria, Pinehurst, Northview, Stephenson, Ashland, and Palos Verdes.
(Authorize the City Manager to finalize and execute a contract with McMahon Contracting, LP, in the amount of $7,507,245.00.)
Body
Name of Department
Public Works - Engineering
Project/Budgeted Amount
$8,000,000.00
Sum of Bid/Bid Amount
$7,507,245.00
On September 30, 2026, the City received eight proposals in response to the Request for Proposals (RFP). The proposals were evaluated based on the following criteria:
• Qualifications of Key Project Personnel
• Similar Project Experience (Past and Current Performance)
• Quality of the Proposer's Goods and Services
• Pricing
Following completion of the evaluation process, McMahon Contracting, LP, was selected for award of the project based on the evaluation criteria.
The contract is anticipated to begin in December 2026, with completion anticipated by November 2027.
Financial Implications
The allocated funding is available from the Real.Texas.Roads. Street Bond and Water and Sewer funds.
Recommended/Desired Action
Staff recommends the City Manager be authorized to finalize and execute a contract with McMahon Contracting, LP.
Attachment(s)
Recommendation Letter
Location Map
Drafter
Tracy Romo
Head of Department
Eric J. Gallt, P.E.