Title
Authorize the City Manager to finalize and execute Amendment No. 1 to the Professional Engineering Services Contract for the Southeast Pump Station Improvements, with Freeman-Millican, Inc., for the additional design and preparation of construction documents in an amount not to exceed $210,000.00.
Body
On April 17, 2025, the City Council approved a Professional Engineering Services Contract with Freeman-Millican, Inc. for the preparation of construction plans and specifications for the Southeast Pump Station in the amount of $956,000.00.
Amendment No. 1, in an amount not to exceed $210,000.00, will provide for construction engineering and management services for the Southeast Pump Station Reconstruction Project.
The total contract amount, including Amendment No. 1, will be $1,166,000.00.
Financial Implications
This project is funding with Water and Sewer Funds.
Recommended/Desired Action
Staff recommends that the City Manager be authorized to finalize and execute Amendment No. 1 to the Professional Engineering Services Contract with Freeman-Millican, Inc.
Attachment(s)
Amendment No. 1
Drafter
Tracy Romo
Head of Department
Eric J. Gallt, P.E.