File #: 25-7737    Version: 1 Name: Bid No. 2025-150 - Roadway Maintenance for Walker/Tripp/Mariposa
Type: Agenda Item Status: Passed
File created: 6/30/2025 In control: City Council
On agenda: 7/21/2025 Final action: 7/21/2025
Title: Bid No. 2025-150 - Roadway Maintenance for Walker Street, Tripp Road and Mariposa Drive. (Authorize the City Manager to finalize and execute a contract with Texas Materials Group, Inc. in the amount of $2,742,183.00.)
Attachments: 1. Recommendation Letter, 2. Bid Tabulation, 3. Location Map

Title

Bid No. 2025-150 - Roadway Maintenance for Walker Street, Tripp Road and Mariposa Drive.

(Authorize the City Manager to finalize and execute a contract with Texas Materials Group, Inc. in the amount of $2,742,183.00.)

 

Body

Name of Department

Public Works - Engineering

 

Project/Budgeted Amount

$3,000,000.00

 

Sum of Bid/Bid Amount

$2,742,183.00

 

The purpose of this project is to construct approximately 4,200 square yards of concrete street pavement and over 16,000 square yards of asphalt pavement across three collector streets. The proposed repair methods include varying sections such as asphalt, asphalt with curb and gutter, concrete, and concrete with monolithic curb. Additional improvements include pavement markings, guardrails, and pedestrian facilities.

 

These sections of roadway were selected based on the Pavement Condition Index (PCI) score and traffic volumes.  In addition, Mariposa Drive and Tripp Road are seen as critical commercial traffic alternate routes due to ongoing US 80 and IH 635 construction in the vicinity.

 

This project is anticipated to begin in August 2025 and to be completed by February 2026.

 

Bid notices were broadcast through the BidNet Direct electronic procurement system, posted on the City’s website, and published in the Daily Commercial Record newspaper.  A total of four responsive bids were received.  Staff has reviewed the qualifications and recommends award of the base bid to Texas Materials Group, Inc.

 

Financial Implications

The contract will be allocated with Street Bonds and Concrete Streets Pavement Preservation Funds.

 

Recommended/Desired Action

Staff recommends the City Manager be authorized to finalize and execute a contract with Texas Materials Group, Inc.

 