File #: 18-3342    Version: 1 Name: Bid No. 2018-037 - Time and Material
Type: Agenda Item Status: Passed
File created: 3/2/2018 In control: City Council
On agenda: 3/19/2018 Final action: 3/19/2018
Title: Bid No. 2018-037 - Annual Facility Maintenance, Time and Material, Repair and Remodeling Contract. (Authorize the City Manager to approve expenditures and finalize and execute all necessary documents in conjunction with services provided by Concord Commercial Services, Inc., JM Construction Solutions, Berger Engineering Company, Boyd Electric, Artex Overhead Door Company, Country Glass and Mirror, Control Systems Consultants, Phillips Lawn Sprinkler Company and MyElyn Contractors in an amount not to exceed $698,000.00.)
Attachments: 1. Bid Tabulation, 2. Scoresheet

 Title

Bid No. 2018-037 - Annual Facility Maintenance, Time and Material, Repair and Remodeling Contract.

(Authorize the City Manager to approve expenditures and finalize and execute all necessary documents in conjunction with services provided by Concord Commercial Services, Inc., JM Construction Solutions, Berger Engineering Company, Boyd Electric, Artex Overhead Door Company, Country Glass and Mirror, Control Systems Consultants, Phillips Lawn Sprinkler Company and MyElyn Contractors in an amount not to exceed $698,000.00.)

 

Body

Name of Department

Administration/Building Services

 

Project/Budgeted Amount

Determined on an “as needed basis”

 

Sum of Bid/Bid Amount

Determined as needed with a total “not to exceed” amount of $698,000.00

 

                     Concord Commercial Contractors, not to exceed $65,000.00

                     JM Construction Solutions, not to exceed $63,000.00

                     Berger Engineering Company, not to exceed $465,000.00

                     Boyd Electric, not to exceed $30,000.00

                     Artex Overhead Door, not to exceed $35,000.00

                     Country Glass and Mirror, not to exceed $10,000.00

                     Control System Consultants, not to exceed $10,000.00

                     Phillips Lawn Sprinkler Company, not to exceed $10,000.00

                     MyElyn Contractors, not to exceed $10,000.00

 

Bid documents were broadcast through BidSync, posted on the City’s website and an Advertisement for Bid notice was published in The Daily Commercial Record newspaper. A total of 18 bids were received.

 

Building Services Division staff utilizes Time and Material contracts for unexpected repairs and/or equipment replacements when contractor response time and repair time is critical and there is no time to solicit informal bids under normal conditions. These types of projects include HVAC equipment repairs and replacement, plumbing repairs and improvements, electrical repairs, roof repairs and replacement, and related carpentry, drywall and painting. At the beginning of each project, a scope of work is reviewed with the contractor and a proposal is requested. Each proposal is submitted as a “not to exceed” amount. Time and Material contracts can save time and aid staff in establishing budget costs for future projects, generate cost savings and expedite emergency repairs that affect municipal operations.

 

Staff evaluated each bid response for recommendation of award to the bidder who provides goods or services at the best value for the City. This contract would be for a one year period with two additional one-year renewal options.

 

Recommended/Desired Action

Staff recommends award to the following responsible and responsive bidders meeting specifications and authorize the City Manager to finalize and execute all necessary contract documents as needed.

 

Concord Commercial Services, Inc.                     Item No. 1 (General Carpentry)

                     Item No. 6 (Plumbing)

JM Construction Solutions                     Item No. 2 (Floor Tile)

                     Item No. 3 (Carpet)

                     Item No. 4 (Laminate Wood Flooring)

                     Item No. 10 (Roofing)

                     Item No. 15 (Stone or Brick Masonry)

Berger Engineering Company                     Item No. 5 (Heating, Venting and Air Conditioning)

                     Item No. 13 (Water Treatment Cooling Towers)

Boyd Electric                     Item No. 7 (Electrical)

Artex Overhead Door Company                     Item No. 8 (Overhead Door Repair)

Country Glass and Mirror                     Item No. 9 (Glass Replacement)

Control Systems Consultants                     Item No. 11 (Building Automation Controls)

Phillips Lawn Sprinkler Company                     Item No. 12 (Irrigation)

MyElyn Contractors                     Item No. 14 (Landscaping)

 

Attachment(s)

Bid Tabulation

Scoresheet

 

Drafter

Larry Ewing

 

Head of Department

Ted Chinn