Title: Discuss results from the public meeting and citizen survey regarding the preliminary design schematic for Town East Boulevard from US Highway 80 to Skyline Drive and for Skyline Drive from Town East Boulevard to Peachtree Road.
Attachments: 1. Survey Results Location Map, 2. Location Map, 3. Cost Estimates for Various Options, 4. Design Option Examples

Title

Discuss results from the public meeting and citizen survey regarding the preliminary design schematic for Town East Boulevard from US Highway 80 to Skyline Drive and for Skyline Drive from Town East Boulevard to Peachtree Road.

 

Body

Prior to beginning the design for Phase 2 of the Town East Blvd. Reconstruction Project, Skyline to US80, staff sought input from residents on the ultimate roadway design.  During this public input period, it was determined that the ultimate design of Skyline Drive from Town East to Peachtree was needed.  Staff developed several roadway schematics to address declining roadway conditions, accommodate existing and future traffic demands and address resident concerns with traffic speeds, safety, noise, vibration and roadway amenities. 

 

As part of the public input process, a public meeting was held on February 27, 2018 at Rugel Elementary School to present various design options and gather input from residents.  Approximately 140 residents attended the meeting.  Following the meeting, staff distributed surveys to all attendees and mailed 1,100 letters to residents in the Skyline/Town East Area.  A video of the public meeting, public meeting materials, and the Traffic Impact Analysis were posted on the City’s website.  An online version of the survey was also made available to residents. 

 

A total of 214 mailed and 56 online surveys were returned to staff.  The survey results are listed below:

 

Town East Blvd. - Skyline to US80

Option A - Four Lane Section with screening wall and trail - 71%

Option B - Six Lane Section with screening wall and sidewalk - 29%

 

Skyline Drive - Town East to Peachtree

Option A - Three Lane Section with dual turn lanes - 33%

Option B - Four Lane Undivided Section - 26%

Option C - Four Lane Divided Section - 33%

Option D - Existing Four Lane Section - 9 %

 

The proposed schedule for the completion of this project anticipates design completion in the fall of 2018 and construction to begin in early 2019. 

 

Recommended/Desired Action

During the Pre-Meeting, Staff is requesting the City Council to provide direction on preferred option to begin final design for the two projects.  Prior to initiation of the design contract, a final public hearing will be held to allow final public input on the decision. 

 

Attachment(s)

Survey Results

Location Map

Cost Estimates for Various Options

Design Option Examples

 

Drafter

Corey Nesbit, P.E.

 

Head of Department

Matthew Holzapfel, P.E.