File #: 23-6469    Version: 1 Name: CMaR Services (Phase I) Animal Shelter Addition
Type: Agenda Item Status: Passed
File created: 2/24/2023 In control: City Council
On agenda: 3/20/2023 Final action: 3/20/2023
Title: Bid No. 2023-040 - Construction Manager at Risk (CMaR) Services for the Construction of Mesquite Animal Shelter and Adoption Center Addition. (Staff recommends award to Falkenberg Construction Company, Inc., and to authorize the City Manager to finalize and execute a contract in an amount not to exceed $2,500.00 for CMaR services in connection with the design (Phase I) of the Mesquite Animal Shelter and Adoption Center Addition.)
Attachments: 1. CMaR Evaluation Criteria and Scoring Summary

Title

Bid No. 2023-040 - Construction Manager at Risk (CMaR) Services for the Construction of Mesquite Animal Shelter and Adoption Center Addition. 

(Staff recommends award to Falkenberg Construction Company, Inc., and to authorize the City Manager to finalize and execute a contract in an amount not to exceed $2,500.00 for CMaR services in connection with the design (Phase I) of the Mesquite Animal Shelter and Adoption Center Addition.)

 

Body

Name of Department

Neighborhood Services/Animal Services Division

 

Project/Budgeted Amount

$2.0 million

 

Sum of Bid/Bid Amount

$2,500.00

 

Falkenberg Construction Company, Inc., submitted a proposal for Construction Manager at Risk (CMaR) services for the design (Phase I) of the Mesquite Animal Shelter and Adoption Center Addition.  Throughout Phase I, the CMaR will work with the City’s contracted architect (GSR Andrade Architects) to analyze the architect’s design to ensure feasibility and constructability, and to keep estimated construction costs within budget without adversely affecting the capacity and quality of the project. The CMaR will propose a Guaranteed Maximum Price (GMP) for the construction of the project after review and possible revisions of the construction documents. The fee for Phase I services is $2,500.00.

 

Upon successful completion of Phase I services, the City of Mesquite may elect to execute a supplemental agreement to contract the CMaR to serve as the general contractor for this project during the construction phase (Phase II). Falkenberg Construction Company, Inc., has bid Phase II services at 28.73 percent of the total construction cost (this service fee includes the general conditions, additional overhead, insurance, bonds, and profit).

 

Notices for this Request for Proposal were broadcast through the Periscope Holdings electronic bidding system, published in the Daily Commercial Record newspaper, and posted on the City’s website.  Four companies submitted proposals for this project.  The four proposals were scored by staff with the top two scoring companies invited to interview. Falkenberg Construction Company, Inc., was the top scored bid after the interviews.

 

Financial Implications

The budget for the Mesquite Animal Shelter and Adoption Center Addition is $2.0 million.  Phase I CMaR fees will be paid from this fund.

 

Recommended/Desired Action

Staff recommends award of contract for Phase I CMaR services to Falkenberg Construction Company, Inc.

 

Attachment(s)

CMaR Evaluation Criteria and Scoring Summary

 

Drafter

Mark Kerby

 

Head of Department

Maria Martinez