File #: 23-6504    Version: 1 Name: Change Order No. 4 to Bid No. 2019-070
Type: Agenda Item Status: Passed
File created: 3/10/2023 In control: City Council
On agenda: 4/3/2023 Final action: 4/3/2023
Title: Authorize the City Manager to finalize and execute Change Order No. 4 to Bid No. 2019-070, Powell Road, Orchid Avenue, Melton Lane, Magnolia Drive, and Douglas Drive Paving and Utility Improvements (Real. Texas. Roads.), with Reliable Paving, Inc., for additional services required in the amount of $49,800.00.
Attachments: 1. Location Map, 2. Change Order No 4 - Powell Road, 3. Change Order Request Form
Title
Authorize the City Manager to finalize and execute Change Order No. 4 to Bid No. 2019-070, Powell Road, Orchid Avenue, Melton Lane, Magnolia Drive, and Douglas Drive Paving and Utility Improvements (Real. Texas. Roads.), with Reliable Paving, Inc., for additional services required in the amount of $49,800.00.

Body
The City Council approved Bid No. 2019-070, Powell Road, Orchid Avenue, Melton Lane, Magnolia Drive, and Douglas Drive Paving and Utility Improvements (Real. Texas. Roads.), with Reliable Paving, Inc., on February 1, 2021, in the amount of $4,293,081.70.

Change Order No. 1 was approved by the City Manager on August 23, 2021, in the amount of $46,469.27 for additional sidewalk, water and sewer items.

Change Order No. 2 was approved by the City Council on December 20, 2021, in the amount of $164,690.00 for additional concrete work.

Change Order No. 3 was approved by the City Council on March 21, 2022, in the amount of $142,532.00 for additional water lines and concrete paving.

Change Order No. 4 is required to increase quantity for existing sidewalk as well as curb and gutter due to conditions in the field. One-hundred-sixty (160) additional calendar days will be added to the contract with this change order. The following is a breakdown of the added calendar days:

100 days - Concrete limitations due to cement shortage
30 days - Locating and adjusting utilities due to inaccuracies in the historical records
20 days - Pumping due to inclement weather
10 days - Additional field layout and replacement of infrastructure not included in plan set
160 days - Total

The current contract amount is $4,646,772.97. Change Order No. 4 is in the amount of $49,800.00, for a revised contract amount of $4,696,572.97. The project is substantially complete, and this will be the final change order required.

Financial Implications
This project is funded by Street Bond Program for paving, Water/Sewer Revenue funds for the utilities, and has adequate funds to ac...